Development Methodologies

The SDLC (software development life cycle) is the sequence of stages a product goes through: planning, requirements, design, implementation, testing, deployment, maintenance. Waterfall goes through them once, in order, which suits fixed and well-known requirements. Agile repeats them in short iterations and adapts the plan to feedback. Scrum and Kanban are the two most common ways to practice Agile: Scrum works in fixed-length sprints with defined roles and events, Kanban is a continuous flow of tasks on a board with limits on work in progress.

Details​

Waterfall vs Agile​

WaterfallAgile
ProcessStages in sequence, each completed onceShort iterations, each through all stages
RequirementsFixed up frontChange between iterations
FeedbackAt the endAfter every iteration
TestingA late separate stageContinuous, from the start ("shift left")
StrengthsPredictable plan, budget and documentationAdapts to change, early value, issues found early
WeaknessesChanges are expensive, problems surface lateScope is harder to fix, needs constant collaboration

Shift-left testing means moving testing earlier in the cycle: defects found during development are cheaper to fix than after release.

Scrum​

Per the Scrum Guide (2020 edition):

  • Roles (accountabilities): Product Owner (orders the Product Backlog, maximizes value), Scrum Master (helps the team follow Scrum, removes impediments), Developers (build the increment).
  • Events: the Sprint (up to a month, usually 2 weeks) contains Sprint Planning, the Daily Scrum (15 minutes), the Sprint Review (the increment shown to stakeholders) and the Sprint Retrospective (how to work better).
  • Artifacts: Product Backlog, Sprint Backlog, Increment.
  • Estimation is not prescribed by the guide; teams often use story points (relative effort) and planning poker.

Kanban​

  • A board with columns for workflow stages (To Do → In Progress → Review → Done).
  • WIP limits: a column can hold only N tasks, so the team finishes work before starting new work.
  • No fixed iterations or roles; tasks are pulled when there is capacity.
  • Measured by lead time (request to done) and cycle time (start to done).

Scrum vs Kanban​

ScrumKanban
CadenceFixed sprintsContinuous flow
RolesProduct Owner, Scrum Master, DevelopersNot prescribed
ChangesNone that endanger the Sprint GoalAny time, by reordering the queue
Limits workBy sprint capacityBy WIP limits per column
FitsProduct development with planningSupport, operations, a stream of small tasks

Follow-up Questions​

  • What is velocity? The amount of work (in story points) a team completes per sprint; used to plan the next sprints, not to compare teams.
  • What is the Definition of Done? A shared checklist an increment must meet: reviewed, tested, documented, deployed to staging.
  • What if the Sprint scope turns out to be too big? The scope is renegotiated with the Product Owner while the Sprint Goal stays; a Sprint is cancelled only when its goal becomes obsolete, and only by the Product Owner.
  • What is backlog refinement? The ongoing work of splitting upcoming items and adding detail and size, so they are ready for Sprint Planning; it is not a Scrum event.

Common Mistakes​

  • Calling Agile a methodology: it is a set of values and principles (the Agile Manifesto); Scrum and Kanban are ways to apply them.
  • "Development Team" and "ceremonies": the 2020 Scrum Guide says Developers and events.
  • Treating the Daily Scrum as a status report to the manager: it is the Developers' check of progress toward the Sprint Goal and their plan for the next day.

See Also​